Being without a bathroom is the part of a refit most people dread. This guide sets out how long a typical UK bathroom job takes, what happens on each day, and how to stop it dragging on.
A straightforward refit of a standard bathroom — same layout, one dedicated fitting team — usually takes 5 to 10 working days. A small bathroom with minimal tiling can be done in under a week; a luxury bathroom or one with a layout change more often takes two to three weeks.
If your fitter brings in separate trades (plumber, electrician, tiler, plasterer) on different days, expect the job to run over more calendar days even if the working time is similar, because there will be gaps between visits.
| Stage | What happens | Typical time |
|---|---|---|
| Strip-out | Old suite, tiles and flooring removed; water isolated | 1 – 2 days |
| First fix | New pipework, wastes and cables run before walls are closed | 1 – 2 days |
| Boarding and plastering | Walls boarded or skimmed; shower areas waterproofed | 1 – 3 days (plus drying time) |
| Tiling or panelling | Walls and floor tiled and grouted, or wall panels fitted | 1 day (panels) to 5 days (full tiling) |
| Second fix | Toilet, basin, bath or shower, taps, radiator and lights connected | 1 – 2 days |
| Finishing | Sealant, accessories, decorating and snagging | 1 day |
Kartell Complete Bathroom Suite – 1700mm Bath, Low Level Toilet, Basin & Taps – Chrome
£411.87
View product
AKW Alveo 600mm PVC Wall Panels – 2500mm High – Pack of 2 – White Gloss, Marble, Concrete & Graphite
£124.95
View product
Nuie White Slip-Resistant Slimline Square Shower Tray (All Sizes)
From £144.00
View product
Kartell K-VIT Options 550 Short Projection Toilet – Pan Only or Complete WC (POT078OPR)
From £106.20
View product
Yes, if the layout stays the same, all products are on site before work starts and one team does the whole job. Wall panels rather than full tiling make a one-week refit much more achievable.
Usually only for part of the job. Many fitters reconnect the toilet at the end of each day or refit it early. Ask your fitter to plan for this before work starts.
Full wall and floor tiling in an average bathroom typically takes three to five days, including grouting. Large-format or patterned tiles can take longer.